Demanding phase of works at MHPP Bočac 2 started

News | Mart 12, 2018

Elnos Group teams entered a demanding phase of performing assembly of electrical-mechanical and hydro-mechanical equipment within project of constructing MHPP Bočac 2.
At the moment, we are finishing up installation of plate valves thanks to which conditions for undisturbed work of assembling turbine generators will be created, regardless hydrological situation.
Mounting of 50 tons portal crane completed as well thus creating conditions for starting assembly of both turbine generators parts.
We would like to remind this is the first project of constructing new hydro-power plant, where our company is the leader of entire electrical-mechanical and hydro-mechanical phase.
We perform this project as the Main Contractor cooperating with the Investor ZP Hidroelektrane na Vrbasu a.d. Mrkonjić Grad and our consortium partner Andritz Hydro S.A.S. Contract for delivery and installation of electrical-mechanical and hydro-mechanical equipment for MHPP Bočac 2, includes making production technical documentation, delivery and assembly of equipment and function testing as well as hydro-power plant commission.
Project significance
Construction of MHPP Bočac 2 is a development project of multi-significance for the system of Elektroprivreda RS and economy of Mrkonjić Grad. About 50 per cent of electrical power is spent whereas only five per cent is produced within Elektroprivreda RS in the West part of the Republic of Srpska (RS). Construction of MHPP Bočac 2 shall change this ratio and create conditions for more reliable supply of electrical power in this part of the Republic of Srpska.