Implemented a new project in Macedonia

News | Novembar 30, 2017

The Macedonian member of Elnos Group, the company Elnos BL Skopje, has successfully implemented the project reconstruction of part of the 400 kV transmission line from the substation Dubrovo to the Macedonian-Greek border. The reconstruction of this part of the transmission line has created the conditions for the long-waited release of the traffic section of Pan-European Corridor 10, stretching from Demir Kapija to Smokvice 28.2 kilometers long.
The biggest challenge for our team at the field was the short deadline for the works executions, imposed by the necessity of excluding of the international transmission line during the realization of this project. Nevertheless, thanks to good organization, our team were successfully completed all works in the contracted deadline. The disassembly of the part of existing 400 kV transmission line was done within 15 days. The installation of four new transmission lines, with the relocation of the entire transmission line route, was carried out within a month.
This project is specific due to the fulfillment of technical regulations and aviation regulations for transmission lines that interfere with highways. Therefore, the new transmission line is higher, the pillars are painted according to the regulation, between them are marking balls, and lamps are installed on the top of the pillars.
Contract for the implementation of the reconstruction of part of the 400 kV transmission line from the substation Dubrovo to the Macedonian-Greek border is the first project which Elnos BL Skopje realized for the Greek company “Aktor” ADT.