110 kV Veles–Ovče Polje transmission line reconstruction – enhancing energy stability in North Macedonia

In the heart of North Macedonia, between the cities of Veles and Ovče Polje, reconstruction of a key 110 kV transmission line, originally built more than half a century ago, has been completed. This 21-kilometer-long line has now been modernized to ensure more stable and reliable electricity supply for the regions of Sveti Nikole and Veles.

Transmission lines
Veles - Ovče Polje
elnos group

Project overview

Elnos Group teams played a key role in this major undertaking, which required the dismantling of old concrete towers and the construction of new steel lattice towers along a significant portion of the route. The works were carried out with maximum precision and dedication to ensure the quality and long-term durability of the infrastructure.

elnos group

Technical characteristics

  • Transmission line voltage: 110 kV
  • Length of reconstructed line: 21 km
  • Replacement of old concrete towers with new steel lattice towers
  • Modernization of power-system components
  • System adaptation to enable integration of renewable energy sources
elnos group

Implementation challenges

  • Work on existing infrastructure more than 50 years old, requiring careful planning and execution
  • Coordination of works across different sections of the route while maintaining grid stability
  • Optimization of the transmission line route to improve electricity transmission efficiency
  • Compliance with environmental standards, considering that the line passes through agricultural land and that land impact had to be minimized
elnos group

Elnos Group’s role

Elnos Group played a key role in project implementation through the following activities:

  • Dismantling of old concrete towers and construction of new steel towers
  • Modernization of protection and control systems
  • Optimization of power transmission through improved technical solutions
  • Testing and commissioning of the reconstructed transmission line
elnos group

Strategic importance

  • Increased security of electricity supply in the regions of Sveti Nikole and Veles
  • Integration of new renewable energy sources into North Macedonia’s power system
  • Reduction of electricity transmission losses, improving overall network efficiency
  • Long-term stability of power infrastructure, enabling reliable supply for households and industry

The reconstruction of the 110 kV Veles–Ovče Polje transmission line represents a key step in strengthening North Macedonia’s energy infrastructure, improving network capacity and enabling easier integration of renewable energy sources.

General Information

Year 2023
Investor Macedonian Electricity Transmission System Operator (MEPSO)
Status Završeno
Location Veles - Ovče Polje
Length 21 km