Skip to content

Construction of 220 kV transmission line Þeistareykjalína 1 and 220 kV Kröflulína 4

The significance of the project:
Responsibility for the construction of 220 kV transmission line Þeistareykjalína 1 and 220 kV Kröflulína 4 imposed a new factory energy needs of electrode factory, built near the town of Husavik, in the north of Iceland.

Elnos Group works:
Elnos Group in the framework of this project assembled and installed 192 poles which was built transmission line route 62 kilometers long. In the context of this complex project it was set nine different types of poles whose weight varied from 5.5 to 26 tons. Also, the project is specific because on the transmission lines were installed tubular portal poles with braces.

 

 

 

 

 

 

 

 

 

 

General Information

Year 2017.
Investor ”LANDSNET”, Iceland
Status Completed
Country Iceland
Location Region of northern Iceland