Construction of the transmission line 2 x 110 kV TL- Bršljin-TL Gotna vas

  • Zemlja: Slovenia
  • Lokacija: Novo Mesto
  • Godina: 2016.
  • Investitor: Elektro Ljubljana
  • Glavni ugovarač: C&G, Ljubljana
  • Status: Finished

The significance of the project:
The construction of the transmission line 2 x 110 kV TL-Bršljin-TL Gotna vas in a 110 kV voltage level is carried out the connecting of transmission lines Bršljin and Gotna vas. This project created the conditions for the future, to make a connection to the substation Ločna and Cikava.

Elnos Group works:
This project involved works on the installation and lifting double circuit 110 kV transmission lines. It is interesting that Elnos Group teams under this project installed even five types of the pillars.