Izgradnja novog DV 130 kV Saxen-Flatenberg

  • Zemlja: Švedska
  • Godina: 2014.
  • Investitor: Vattenfall Eldistribution AB, Švedska
  • Glavni ugovarač: Linjemontage i Grastorp AB, Švedska
  • Status: završeni radovi

Elnos Group works:

On the project of building a new transmission line 130 kV Saxen-Flatenberg Elnos Group performed the works of installation phase conductors and OPGW. The total length of TL is about 25 km, and the installation was completed for a month. At existing wooden towers we installed the conductors 910 mm2, OPGW 125 mm2 and earth wire Dotteral 142 mm2.