The significance of the project
Project covered adjustment to a new control system − SCADA, with delivery and installation of necessary communication and control equipment as well as upgrade of the current control system.
Elnos Group works
Contract included making project documentation for construction and electrical phase, old equipment dismantling and installation of new equipment for control and protection of generator. Likewise, this project also covered adjustment to a new control system − SCADA, with delivery and installation of necessary communication and control equipment as well as upgrade of the current control system.
Project was performed in very complex conditions due to the need for 400 kV bus bars to be energized during work performance. This form of work demanded extreme caution in performing corrections of the existing system.
Likewise, we performed generator bay functional testing and commissioning, so that the Thermal Power Plant Ugljevik would be ready for connection to 400 kV power line and transfer of electricity after overhaul.