- Zemlja: Sweden
- Lokacija: Sweden
- Godina: 2012.
- Investitor: Vattenfall and E.ON, Sweden
- Glavni ugovarač: Ratel Enterprenad, Sweden
- Dužina: 11 km

The project significance
This is one of our first projects at the Swedish ground and it is very important and represents an important move of Elnos Group toward Nordic and EU markets.
Elnos Group works
On the transmission line 2×130 kV Barkeryd – Nässjö Elnos Group were executed complete works, that is, demounting of the existing poles, phase conductors and protective ropes, then: mounting and lifting the poles, installation of two systems of phase conductors and installation of OPGW rope.
During the project in front of us were standing many challenges. The terrain itself is extremely specific and demanding, with many lakes and natural bogs and sloughs. Routes of the transmission lines was very demanding with many crossings with other existing transmission lines, local roads and motorway. As well, the routes pass through many historical findings which can be found in the City of Nässjö and its surrounding in abundance.