- Zemlja: Bosnia and Herzegovina
- Lokacija: Laktaši
- Godina: 2015/2016.
- Investitor: Elektroprenos BiH
- Status: Finished
- Tip: "Turn-key"

Project importance:
Development of industrial zone in Aleksandrovac, Airport Mahovljani, as well as construction of Highway Banja Luka-Gradiška, led to need for construction of new substation in the area of Municipality of Laktaši. Construction of substation 110/20 kV Laktaši 2 provides better supply of electrical power for entire industrial zone within this local community.
Elnos Group activities:
Elnos Group is a part of consortium Elektroenergetika, which constructed a new substation 110/20 kV Laktaši 2 for Investor Elektroprenos BiH.
The following works were performed by Elnos Group during construction of new substation in Laktaši: assembly of primary equipment 110 kV and delivery and assembly of 20 MVA energetic transformer. Apart from this, we performed a part of works referring to calibration of entire 110 kV plant, as well as connection of cables with HV equipment and cabinets for protection and control. We are talking about state-of-art cabinets for protection and control for 110 kV bays, which were made in our electrical mechanical workshop.