In the service of a better supply of the city Užice

News | January 28, 2020

Elnos Serbia teams began with the realization of the great project of building substation 110/35/10 kV Užice 2. It is about an electric power unit which will be in the future an important degree of stability of the power system in the city Užice.
Currently supplying this city, which is the center of the Zlatibor district, takes place over several highly loaded voltage lines and 110 kV transmission line from the direction of the Požega.
The construction of the new substation Užice 2 to the network will be connected 110 kV transmission line from the direction Sevojna, which will become an important link for secure long-term electricity supply of the city. This important project of Elnos Serbia performed as leader of the consortium of six companies engaged in its implementation, and our team at the site currently performed extensive construction works.
Generally speaking our terms of reference within the building Užice 2 SS includes drafting technical documentation, procurement of electrical equipment, construction and electrical installation works and testing and commissioning the substation into operation.
The project investor is ODS “Electric Power Industry of Serbia”, a branch of Užice, a project schedule is foreseen that the works should be completed in September next year.