The reconstruction of new section Railway Corridor 10 through Serbia

News | November 25, 2019

Reconstruction of the section Jajinci-Mala Krsna, the part of the international railway Corridor 10 through Serbia, this fall is in full swing. It is one of the priority projects important for the Serbian railway network whose performing will raised speed and security in this part of the railway Corridor 10 to the necessary level.

Elnos Group teams in the context of this complex project have tasks to reconstruct: contact network, the electric substation 110/25 kV, all plants for sectioning 25 kV on this section, and the construction of new tower-mounted substations 25 kV for the power supply device for signaling.

Elnos team will dissembled and assembly of almost 70 kilometers overhead line, while the 25 kilometers of the existing contact network dissembled old items for carrying and tightening the contact network and replace them with new ones.

Completely will be implemented and replacement of electrical equipment at four plants for sectioning and electric substation, reconstruction also includes construction of seven new tower-mounted substations whose role is to supply signaling devices and heating for crossover.

Trains speed on the railway section Jajinci-Mala Krsna, 58 kilometers long, after the reconstruction will be increased from 50 to 120 kilometers per hour.
Investor of the project is “Infrastructure Serbian Railways”, and the main contractor companies are “Colas Rail” and “Energoprojekt niskogradnja”.
The entire project according to the approved schedule of works should be completed in early fall of next year.